Dynamic Wire Free Strain
Gauge Monitoring System (DSGS)
as used in Solar Power
High Tension Transmission Lines
In September 08 the developers of
the Dynamic Wire Free Strain Gauge Monitoring System were
approached by a senior VP Litigation Attorney for one of the
large Insurance firms in the US, regarding a law suit for a
staggering 1.5 billion (USD). The law suit resulted from fires
that were caused by the combination of excessive fatigue in the
electric Utility Transmission lines and Santa Ana winds that
resulted in overstretched transmission lines clashing and
creating sparks that ignited the surrounding vegetation.
The general discussion became focused on the Dynamic Wire Free
Strain Gauge Monitoring System being placed on high tension
transmission lines, to monitor stress and strain, with the
potential to becoming a standard for the industry.
The key issue identified was the maintenance on the transmission
lines. From discussions it was revealed that a standard formula
is applied to calculate sag in power lines, but this is based on
averages, and the problem is that some lines sag more than
others. Associated to this is the fact that there is no
monitoring system/approach available that can appropriately
differentiate between those lines that need additional
maintenance and those lines that need little maintenance.
With access to 5 top level engineers, the next 2 weeks was spent
analyzing the clashing Transmission wires problem and devising a
solution using the Dynamic Wire Free Strain Gauge Monitoring
System. The solution was presented to the Attorney and several
US Power Companies, who accepted that it would have provided the
Electric Utility in question with the means to avoid the fires
and therefore avoid the $1.5b (USD) litigation.
The solution is based on monitoring the transmission lines to
allow the Utility to decide which lines need additional
maintenance and equally important to have data to pin point
potential problem areas. Since those first meetings, further R &
D has been devoted to identify better ways to power the units,
including the use of Leakage from the power lines to power the
units, coupled with Battery backup.
Further analysis, and field based testing, is required to
identify the optimum number of sensors needed on the lines
between each tower, and where they should be positioned,. To
this end it is believed the Utility Maintenance Engineers, with
their wealth of knowledge and experience in the industry, could
provide significant input into the correct placement of the
sensors.
The other area of concern raised at the time was the maintenance
of the Transmission Towers themselves. The resultant discussion
identified that fatigue analysis on towers is easily solved
using the Dynamic Wire Free Strain Gauge Monitoring System as
well.
With all this in mind it is believed that the best approach,
moving forward, is a Utility based project to enable field based
testing of the alternative positioning options to identify the
optimum placement of sensors to meet specific Utility
requirements. |